Originally published as: Creating Thermal Breaks to Prevent Heat Conduction

Steel is one of the best structural materials in the building industry — and one of the worst insulators. A framing member that runs from the cold outdoors to the conditioned indoors acts like a metal spoon left in a hot cup of coffee: heat (or cold) travels straight through it, bypassing whatever insulation surrounds it. Engineers call this thermal bridging, and in metal buildings it happens at every purlin, girt, clip, and fastener that touches both the exterior panel and the structural frame. A thermal break interrupts that path, and getting it right is one of the simplest ways a builder can deliver a tighter, more comfortable, less complaint-prone building.

Attakorn-stock.Adobe.com

Why Steel Needs a Thermal Break

Metal conducts heat far more efficiently than the wood or masonry alternatives builders typically detail around. Cold-formed steel framing, in particular, transfers heat at a rate many times greater than comparable wood members, which is why insulation strategies that work in a stick-framed wall often underperform when the same R-value is compressed against steel.

In a typical metal building systems, roof panels attach to purlins and wall panels attach to girts. Fiberglass metal building insulation is draped over or behind those members and then compressed flat the moment panels are screwed down. At each compression point, the insulation’s effective thickness—and therefore its R-value—drops sharply. Left unaddressed, that repeated compression can cut a wall or roof assembly’s actual thermal performance is negatively affected &/or is reduced when fiberglass insulation is compressed beyond the thickness to allow it’s intended R-value.

The consequence isn’t just a higher energy bill. Steel framing members that stay in contact with cold outside air become cold spots on the interior face. When warm, humid indoor air reaches those cold spots, it condenses — and condensation on purlins, girts, and fasteners is one of the most common causes of rust, stained insulation facing, and callbacks in the metal building industry.

Where Thermal Bridges Form

Clips and standing-seam attachment points, where metal-to-metal contact runs straight through the insulation layer

Base plates, eave connections and wall-to-roof transitions, where inside and outside skins meet

Fasteners and screws that penetrate the full assembly, each one a tiny, repeated bridge across the envelope

Thermal Spacer Blocks and Thermal Break Strips

The most direct fix at a purlin or girt connection is a thermal spacer block — a rigid strip of extruded polystyrene or similar closed-cell foam installed between the metal panel and the framing member. Instead of panel meeting steel meeting compressed insulation, the spacer block holds a layer of low-conductivity material at the exact point where the bridge would otherwise form, preserving the insulation’s loft on either side of the connection.

Industry guidance published jointly by the North American Insulation Manufacturers Association and ASHRAE calls for a minimum R-3 thermal spacer block at these connections in most conditioned metal building assemblies, with thinner thermal break strips acceptable only where continuous insulation is also present. Spacer blocks are typically installed in standard widths of about three inches and thicknesses between a half-inch and one inch, sized to the purlin or girt flange they’re protecting.

Continuous Insulation: The Belt-and-Suspenders Approach

Where energy codes demand more performance than a spacer block alone can deliver, continuous insulation (CI) is the industry’s standard answer. ASHRAE defines continuous insulation as insulation that runs uncompressed across all structural members without thermal bridges other than fasteners and service openings — in practice, a layer of rigid board applied to the exterior face of the framing, outside the purlins and girts entirely, so the steel never has an uninterrupted path to the outdoors.

Continuous insulation systems have become more common in metal buildings over the past decade as commercial energy codes — chiefly ASHRAE 90.1 and the International Energy Conservation Code — have tightened. A rigid board system installed over the framing, combined with a compressed fiberglass layer inside, gives builders a way to meet required U-factors without relying on a single insulation layer to do all the work.

Thermal Breaks in Cold-Formed Steel Framing

The same principle applies at a larger scale in cold-formed steel (CFS) buildings, where thermal strips, shims, and slotted studs are used at structural connection points to reduce metal in direct contact with heat-exposed surfaces. Cladding attachment systems—clips and girts that hold exterior panels to the frame—can become significant thermal bridges if they aren’t isolated from the structure, which is why thermally broken attachment hardware has become standard detailing on well-designed CFS envelopes.

Getting the Detail Right on the Jobsite

Specify the thermal break material, thickness, and R-value on the structural or insulation drawings — don’t leave it to field judgment

Install spacer blocks or thermal strips at every purlin and girt connection, not just at a sample of locations

Avoid compressing insulation flat at fastener points; a properly seated spacer block keeps the insulation at its rated loft

Pair thermal breaks with a continuous, sealed vapor retarder — a thermal break reduces cold spots, but it doesn’t replace vapor control

Verify assembly U-factors against ASHRAE 90.1 or IECC tables for the local climate zone before panels go up

None of this requires exotic materials or specialized labor. A thermal spacer block is inexpensive, installs in the same motion as the panel screw-down, and pays for itself the first winter the building doesn’t sweat. Historically, the higher cost has come from builders not knowing the detail existed—or assuming a thick enough insulation batt would compensate for a steel frame that was never isolated from the weather in the first place. It won’t. The break has to be built in.


Sources and Resources